Quiz Question 1 of 5
If something comes up that is important but is not in the sprint, what should the Scrum Master do?
Choose the correct answer below:
-
A
Put the item in the sprint backlog for everyone to see.
-
B
Ask the team whether it is something that can be done within the Sprint.
-
C
Find something in the Sprint that can be removed to accommodate the new item.
-
D
Ask the Product Owner to add it to the product backlog.
-
E
Step in and make sure the item gets done.